Council received a report on Forty six (46) on-going Capital Projects in the University as at 6th May, 2011.

Council noted that out of the 46 projects, seven (7) had been completed and handed over to the University, ten (10) has been completed but still waiting final inspection and official handing over, while twenty nine (29) were still at various stages of completion.

Council also noted that some of the projects were behind schedule as some of the Contractors faced problems ranging from topographical problem of the sites to the Bill of Quantities and other contracts associated problems.

Council noted the information that the University Management had already taken a stand that contractors who were behind schedule by sixteen (16) weeks and above would not be considered for award of any contracts until they complete the ones they were currently handling.

Council commended Management for the efforts in ensuring the completion of the projects with quality and the level at which the remaining ones were, even as the Federal Government did not release funds as promised.

Council noted the report of all the on-going Capital Projects as at 6th May, 2011.

Last Updated on June 8, 2011 by admin

Author

Times Higher Education (THE)
World University Rankings (WUR) for 2024

rANKING OF UniversitIES of Agriculture

1ST IN aFRICA | 7TH gLOBALLY

30th Convocation Ceremonies

Award of First Degree to deserving graduands

Days
Hours
Minutes
Seconds