8.5 Ratification of Executive Approvals
Last Updated on June 8, 2011 by admin Council ratified the executive approval of the Vice-Chancellor on the following cases: i. Renewal of Contract Appointment – Dr. F. A. Oguntoye, Director, Information and Communication Technology Resource Centre (ICTREC). ii. Upgrading from the post of Junior Research Fellow to Assistant Lecturer: Mr. O. O. Ajani, Dept. […]
6.8 Fund for the Completion of FGN 2010 Capital Projects
Last Updated on June 8, 2011 by admin Council received a proposal on the modalities for the completion of FGN 2010 Capital Projects. Council noted the amount initially approved for UNAAB in the 2011 FGN capital grant which was later reviewed downward with only 54% thereof appropriated. Council noted the total value of contracts awarded […]
6.7 Proposed Capital Projects
Last Updated on June 8, 2011 by admin Council received a list of thirty-two (32) capital projects being proposed as enumerated in the table below for consideration and approval. S/N Type of Project Justification for the project Source of Funding Remarks 1. Proposed completion of College of Veterinary Medicine (COLVET) Building (Phase II) To provide […]
6.6 Construction of 2,500-Seater Capacity Auditorium Complex
Last Updated on June 8, 2011 by admin Council received a report of additional work on the contract for the construction of 2,500-Seater Capacity Auditorium. Council noted that it had earlier approved the project thus: Contractor – Messrs Nidave industrial Ventures Limited Consultant – Messrs Peogat Engineering Council noted the report that in the course […]
6.3 External Auditors Report On Domestic Report & Audited Financial Statements for the Year Ended 30th June, 2009
Last Updated on June 8, 2011 by admin Council received the report of the External Auditors on the Domestic Report and the Audited Financial Statements for the year ended 30th June, 2009. Council was informed that plans were already at an advanced stage to align the University’s financial year with the Federal Government’s which begins […]
6.4 Reconstruction of the Ceremonial Road
Last Updated on June 8, 2011 by admin Council received a report that additional work needed to be done on the reconstruction of the Ceremonial Road for the overall satisfactory performance of the finished work. Council recalled its earlier approval that the project be awarded as follows: Contractor: Messrs Oriental Femab-Amimike Quarry and Construction Ltd. […]
6.5 Construction of Administrative Building for Farm Centre
Last Updated on June 8, 2011 by admin Council received a report of under-measurement of some items in the Bills of Quantities and additional works on the contract for the construction of Administrative Building for Farm Centre. Council recalled that it had earlier approved the contract for the construction of Administrative Building for Farm Centre […]
5.0 INSPECTION OF BOARDABLE ITEMS:
Last Updated on June 8, 2011 by admin Council received a list of inspected vehicles and some economically unserviceable items suggested for boarding. Council however observed that the report did not contain the date of the purchase of the vehicles, to determine their present economic values. Council approved in principle, the boarding of the vehicles […]
6.1 Statement of Cashbook Balance as at 27th April, 2011
Last Updated on June 8, 2011 by admin Council received the statement of University Cashbook balance as at 27th April, 2011. Council noted that the University had been meeting its obligations as at when due and its finances were not threatened. Council noted that the Federal Government released only about 23% of the original Capital […]
6.0 RECOMMENDATIONS FROM THE FINANCE AND GENERAL PURPOSES COMMITTEE (F&GPC)
Last Updated on June 8, 2011 by admin The Finance and General Purposes Committee (F & GPC) at its meeting held on Wednesday, 11th May, 2011 considered a wide range of matters brought before it by the University Management and made the following recommendations to Council for approval:
6.2 Proposed Construction Of Porter’s Lodge/Linkway Connecting Block ‘D’ With The New Hostel Donated By Rt. Hon. Dimeji Bankole
Last Updated on June 8, 2011 by admin Council received a report that the University was proposing to construct a Porter’s Lodge/Linkway connecting Block ‘D’ with the new Female Hostel donated by Rt. Hon. Dimeji Bankole Council noted the importance of the project as it will enhance the beauty of the hostel environment and also […]
4.0 ANALYSIS REPORT BY THE INTERNAL AUDIT ON CAPITAL PROJECTS.
Last Updated on June 8, 2011 by admin Council received an analysis report from the Internal Audit Unit, through the University Management, on Capital Projects, in relation to the price(s) of the contracts. Council noted the importance of the Unit in the University, being the Financial Control Unit of the University. Council noted that the […]