6.9 Main Entrance of the COLERM (Phase II) Building

Council received a report on the Main Entrance of the COLERM (Phase II) building. Council noted the observation that the entrance to a College Building was expected to have a proper transit area as landing and distinct in appearance to give the approach identity of an entrance to the building. Council noted the following as […]

8.5 Ratification of Executive Approvals

Council ratified the executive approval of the Vice-Chancellor on the following cases: i. Renewal of Contract Appointment – Dr. F. A. Oguntoye, Director, Information and Communication Technology Resource Centre (ICTREC). ii. Upgrading from the post of Junior Research Fellow to Assistant Lecturer: Mr. O. O. Ajani, Dept. of Plant Breeding & Seed Technology Mr. A. […]

6.8 Fund for the Completion of FGN 2010 Capital Projects

Council received a proposal on the modalities for the completion of FGN 2010 Capital Projects. Council noted the amount initially approved for UNAAB in the 2011 FGN capital grant which was later reviewed downward with only 54% thereof appropriated. Council noted the total value of contracts awarded under the reviewed 2010 capital appropriation out of […]

6.7 Proposed Capital Projects

Council received a list of thirty-two (32) capital projects being proposed as enumerated in the table below for consideration and approval. S/N Type of Project Justification for the project Source of Funding Remarks 1. Proposed completion of College of Veterinary Medicine (COLVET) Building (Phase II) To provide for offices for staff in the College EGE […]

6.6 Construction of 2,500-Seater Capacity Auditorium Complex

Council received a report of additional work on the contract for the construction of 2,500-Seater Capacity Auditorium. Council noted that it had earlier approved the project thus: Contractor – Messrs Nidave industrial Ventures Limited Consultant – Messrs Peogat Engineering Council noted the report that in the course of executing the project, it became imperative to […]

6.4 Reconstruction of the Ceremonial Road

Council received a report that additional work needed to be done on the reconstruction of the Ceremonial Road for the overall satisfactory performance of the finished work. Council recalled its earlier approval that the project be awarded as follows: Contractor: Messrs Oriental Femab-Amimike Quarry and Construction Ltd. Consultant: Messrs ALF & Partners Council however noted […]

6.5 Construction of Administrative Building for Farm Centre

Council received a report of under-measurement of some items in the Bills of Quantities and additional works on the contract for the construction of Administrative Building for Farm Centre. Council recalled that it had earlier approved the contract for the construction of Administrative Building for Farm Centre thus: Contractor: Messrs Shegs Contracts Limited Consultant: Messrs […]

5.0 INSPECTION OF BOARDABLE ITEMS:

Council received a list of inspected vehicles and some economically unserviceable items suggested for boarding. Council however observed that the report did not contain the date of the purchase of the vehicles, to determine their present economic values. Council approved in principle, the boarding of the vehicles and other items in the list subject to […]

6.1 Statement of Cashbook Balance as at 27th April, 2011

Council received the statement of University Cashbook balance as at 27th April, 2011. Council noted that the University had been meeting its obligations as at when due and its finances were not threatened. Council noted that the Federal Government released only about 23% of the original Capital Grants approved for the University in 2010. Council […]

Times Higher Education (THE)
World University Rankings (WUR) for 2024

rANKING OF UniversitIES of Agriculture

1ST IN aFRICA | 7TH gLOBALLY

30th Convocation Ceremonies

Award of First Degree to deserving graduands

Days
Hours
Minutes
Seconds